(Created page with "{{Activity |Date=2021/08/11 |Person=Kevin }} ==Context and Goal== * Yesterday I moved my working progress into Process/K8s Installation/Ingress. There is still much unstr...")
 
Line 3: Line 3:
|Person=Kevin
|Person=Kevin
}}
}}
==Context and Goal==
==Context ==
* Yesterday I moved my working progress into [[Process/K8s Installation/Ingress]].  There is still much unstructured information left to be organized.  
* Yesterday I moved my working progress into [[Process/K8s Installation/Ingress]].  There is still unstructured information left to be organized.  However, as there are a lot of data, organizing everything is infeasible. The priority should base on context and goal, which is to communicate and document the process.  
* Ben still doesn't know how I was doing on the Ingress task.  
* For communication, an overview of the concerning K8s structure is required.  Also, documentation on how I was doing is required.  Last, the communication directing to Ben, which contains the decision whether to continue on ALB or step back to Nginx, is required.
* Whether to use ALB or not is t
 
== Goal ==
* Turn the working progress into communicable pages.   
 
== Success Criteria ==
* The process could benefit the next similar process.
 
 
== Output ==
* ALB structure 
[https://d2908q01vomqb2.cloudfront.net/ca3512f4dfa95a03169c5a670a4c91a19b3077b4/2018/11/20/image1-1.png]
* The overview of my working progress
* Decision whether to progress ALB.
** Decision Template.
 
 
 
 


==To-Do==
==To-Do==
Line 13: Line 30:


==Conclusion==
==Conclusion==
== Meta ==
* How to conceptualize things?
* [[Ideation/Meaning Group]]
[[Category:Daily Document]]

Revision as of 06:45, 11 August 2021

Date 2021/08/11
Person Kevin


Context

  • Yesterday I moved my working progress into Process/K8s Installation/Ingress. There is still unstructured information left to be organized. However, as there are a lot of data, organizing everything is infeasible. The priority should base on context and goal, which is to communicate and document the process.
  • For communication, an overview of the concerning K8s structure is required. Also, documentation on how I was doing is required. Last, the communication directing to Ben, which contains the decision whether to continue on ALB or step back to Nginx, is required.

Goal

  • Turn the working progress into communicable pages.

Success Criteria

  • The process could benefit the next similar process.


Output

  • ALB structure

[1]

  • The overview of my working progress
  • Decision whether to progress ALB.
    • Decision Template.



To-Do

Progress

Conclusion

Meta