Difference between revisions of "LKPP/Draft Timeline"

From PKC
Jump to navigation Jump to search
(Created page with "=Draft Timeline= Below is the draft of PKC Proof Of Concept Timeline, as per discussion on 18-Sep-2022 :19/09 to 21/09 - Find out internal and external procedure in LKPP Organization :19/09 - Write in all the found documentation into pkc.pub, and setup some Portal Page for LKPP Landing Page :22/09 to 25/09 - in Pararel, developer team will finish the design of LKPP Blockchain system :26/09 to 15/10 - Will finish blockchain smart contract with simple UI/UX :17/10 to 31/19...")
 
Line 7: Line 7:
:17/10 to 31/19 - Wrap up with better UI/IX designed by pensieve
:17/10 to 31/19 - Wrap up with better UI/IX designed by pensieve
:Deadline end of October
:Deadline end of October
=Functional and Specification=
Below are the high-level specification that agreed upon to produce workable Proof Of Concept system
# Process of uploading the Product into eCatalogue [Catalogue push to blockchain]
# Ordering Processs of GOods and Services [Push to blockchain]
# Creating contract between Vendor and Government Body [Push to blockchain]
# Proof of order fulfillment [Push to blockchain]
# Payment process after fulfillment according to contract using Cryptocurrency [This one proposed by Donald's team]


=References=
=References=

Revision as of 10:23, 20 September 2022

Draft Timeline

Below is the draft of PKC Proof Of Concept Timeline, as per discussion on 18-Sep-2022

19/09 to 21/09 - Find out internal and external procedure in LKPP Organization
19/09 - Write in all the found documentation into pkc.pub, and setup some Portal Page for LKPP Landing Page
22/09 to 25/09 - in Pararel, developer team will finish the design of LKPP Blockchain system
26/09 to 15/10 - Will finish blockchain smart contract with simple UI/UX
17/10 to 31/19 - Wrap up with better UI/IX designed by pensieve
Deadline end of October

Functional and Specification

Below are the high-level specification that agreed upon to produce workable Proof Of Concept system

  1. Process of uploading the Product into eCatalogue [Catalogue push to blockchain]
  2. Ordering Processs of GOods and Services [Push to blockchain]
  3. Creating contract between Vendor and Government Body [Push to blockchain]
  4. Proof of order fulfillment [Push to blockchain]
  5. Payment process after fulfillment according to contract using Cryptocurrency [This one proposed by Donald's team]