LKPP/Draft Timeline
Revision as of 13:24, 18 September 2022 by Emhavis (talk | contribs) (Created page with "=Draft Timeline= Below is the draft of PKC Proof Of Concept Timeline, as per discussion on 18-Sep-2022 :19/09 to 21/09 - Find out internal and external procedure in LKPP Organization :19/09 - Write in all the found documentation into pkc.pub, and setup some Portal Page for LKPP Landing Page :22/09 to 25/09 - in Pararel, developer team will finish the design of LKPP Blockchain system :26/09 to 15/10 - Will finish blockchain smart contract with simple UI/UX :17/10 to 31/19...")
Draft Timeline
Below is the draft of PKC Proof Of Concept Timeline, as per discussion on 18-Sep-2022
- 19/09 to 21/09 - Find out internal and external procedure in LKPP Organization
- 19/09 - Write in all the found documentation into pkc.pub, and setup some Portal Page for LKPP Landing Page
- 22/09 to 25/09 - in Pararel, developer team will finish the design of LKPP Blockchain system
- 26/09 to 15/10 - Will finish blockchain smart contract with simple UI/UX
- 17/10 to 31/19 - Wrap up with better UI/IX designed by pensieve
- Deadline end of October